Wednesday, July 11, 2007

Valero Says Oklahoma Refinery Cracking Unit May Restart in 14 to 16 Days

(Bloomberg) -- Valero Energy Corp., the largest
U.S. refiner, said the fluid catalytic cracking unit at its
refinery in Ardmore, Oklahoma, may start up in 14 to 16 days
after shutting last week.

The start date is a preliminary estimate, Valero spokesman
Bill Day said in a telephone interview. The unit, which was
idled for unplanned maintenance, can process 26,000 barrels a
day of partially processed petroleum.


Read more at Bloomberg Energy News

No comments: